The Darwin area has two weather periods according to then official definitions, wet (green, mud) and dry (brown, dust).
RAAF Aircraft performance unit, some notes on Spitfire tests, date is usually for week ending, serial if given, notes. Note the cowl entries.
26-Aug-42 na First aircraft checked and are properly tropicalised and fitted with flame dampers.
2-Jan-43 A58-110 listed under RAF serial EE610, allotted this date, on 3rd subject to a thorough ground check.
13-Jan-43 A58-110 Tests delayed owing to lack of oxygen mask, as much flying below 18,000 feet as possible. Since arrival of oxygen mask some trouble has been experienced with the airscrews.
27-Jan-43 A58-110 Performance tests in progress.
3-Feb-43 A58-110 Performance tests with 90 gallon belly tanks were carried out.
10-Feb-43 A58-110 Performance tests with 90 gallon belly tanks almost complete. The oxygen mask for this aircraft was stolen whilst hanging out to dry after a high altitude flight. Action taken to obtain further masks.
17-Feb-43 A58-110 Tests proceeding.
24-Feb-43 A58-110 Belly tank trials completed.
10-Mar-43 A58-110 EE610 Under repair after damage received when belly tank became detached in flight. Tests with modified cowl to proceed when cowl available.
17-Mar-43 A58-110 EE610 Repairs completed. Fuel consumption and take off tests alone outstanding.
24-Mar-43 A58-110 EE610 Fuel consumption tests at 15,000 and 25,000 feet and take off tests done. Aircraft undergoing 40 hour inspection.
31-Mar-43 A58-110 EE610 Fuel consumption tests nearly completed, take off tests done. Experimental packing for airscrew tried out in ground run. Packing has so far been unsatisfactory.
7-Apr-43 A58-110 EE610 Flow meter removed for check and refitted and flight tested. Fuel consumption tests nearly completed, take off tests done.
7-Apr-43 A58-110 EE610 Experimental packing for airscrew removed from EE605 after satisfactory ground run and fitted to EE610
14-Apr-43 A58-10 AR621 to go to P&T flt for further G suit trials
14-Apr-43 A58-110 EE610 Tests held up pending manufacture of normal air intake cowlings, airscrew packing tests continuing.
21-Apr-43 na Modified engine cowling, deleting aircleaner, being fitted at SD&F flt, for performance tests.
21-Apr-43 A58-110 EE610 Oil seal washer problem, awaiting modified cowling. airscrew packing giving a lot of trouble.
28-Apr-43 AR621 Currently at 2 OTU, mountings for G-Suit completed and at 1 AD
28-Apr-43 EE610 Unserviceable due to fitting of new cowling and oil seal rings. Airscrew packing still giving trouble.
28-Apr-43 na Modified engine cowling, deleting aircleaner, performance tests begun.
5-May-43 EE610 (In report as EE616) Normal cowl fitted, performance tests near completion, fitting and flight testing of 30 gallon auxiliary tank successfully carried out. Airscrew packing tests continued.
12-May-43 EE610 Normal English Air Intake fitted, climbs to 35,000 feet and level speeds carried out but will be repeated dud to doubtful air temperature readings. fitting and flight testing of 30 gallon auxiliary tank successfuly carried out. Airscrew packing tests continued.
12-May-43 AR621 VHF Radio tests continuing by W/Cdr. Read
19-May-43 na Urgent action to manufacture non tropical engine fairings for one Sqn, another 24 fairings to be made and fitted by 1 June.
19-May-43 EE610 Engine unserviceability caused delay, tests now concluded. Airscrew packing tests continued. No further troubles experienced.
19-May-43 AR621 Being fitted with additional apparatus
26-May-43 EE610 Normal cowl speed tests completed, 5 to 6 mph slower than expected as engine is due for overhaul. The stone grill and air intake and cooler are different to the English design. Airscrew packing tests continued.
26-May-43 EE669 Due to EE610 problems, to be modified for further tests for verification of 380 mph top speed.
26-May-43 AR621 Being fitted with additional apparatus
2-Jun-43 na 24 aircraft fitted with non tropical cowling, remaining reserve aircraft estimated completed by 3 June
2-Jun-43 EE610 Prototype glider towing equipment fitted. Further full throttle level speeds attempted but results appear doubtful, check being made with EE669. Airscrew packing tests continued.
2-Jun-43 AR621 Wired for Cotton (anti G) Suit, S/Ldr Cushing will go to Sydney on 5 June for work on the centrefuge before carrying out tests on Frank and Cotton Suits. Taylor Suit tests continuing.
9-Jun-43 EE610 Tests interrupted by fitting of Prototype glider towing equipment fitted due to be completed in a few days. Airscrew packing tests continued.
9-Jun-43 EE669 Unserviceable due to engine roughness at high altitudes.
9-Jun-43 AR621 Tests on Cotton and Frank suites continued, Frank suit so far appears less effective.
16-Jun-43 na Installation of anti G system in two Spitfires expected by 18 June, one aircraft yet to be delivered. CO2 cylinders not yet indemnified for pressures being used.
16-Jun-43 EE610 Aircraft returned with Prototype glider towing equipment fitted. Airscrew packing tests to be continued when aircraft serviceable.
16-Jun-43 EE669 Faulty throttle linkage adjustments corrected, engine still rough at high altitudes, carburettor being checked.
16-Jun-43 330 Airscrew freezing tests completed, no signs of freezing.
16-Jun-43 AR621 G tests, S/Ldr Cuming underwent a course in the centrifuge at University of Sydney. Flight tests continued. Taylor suit tests continuing.
23-Jun-43 EE610 Used for glider towing successfully, maximum speed 140 mph for glider handicaps general performance.
23-Jun-43 EE669 Carburettor removed for flow checks, due to rough running commencing at 19,000 feet. Fuel pressure gauge being installed in fuel line.
30-Jun-43 EE610 Unserviceable for modification to glider towing gear.
30-Jun-43 EE669 Tank pressure modification carried out.
7-Jul-43 EE669 Engine still very rough at full power above 17,000 feet. Another complete test of throttle being carried out.
7-Jul-43 EE610 Glider towing attachment fitted. Airscrew packing tests continued. Wooden belly tank, the 90 gallon tank did not fit and has been returned to manufacturer.
14-Jul-43 EE610 Further glider tests with E.G.3 held up as glider has damaged wing tip. Airscrew packing tests continued, no trouble has been experienced.
14-Jul-43 EE669 Level speed and climbs at about full throttle height completed. Smooth operation with tropical cowl attained but not with normal cowl. Aircraft allotted away. Tests to be verified on AR621, proposal to lower air intake 3 inches.
14-Jul-43 AR621 No G suit tests done
21-Jul-43 AR621 Test flight to investigate roughness with modified cowl.
21-Jul-43 EE610 Airscrew packing tests continued.
28-Jul-43 EE610 Airscrew packing tests continued with satisfaction.
28-Jul-43 AR621 Anti G suits, to Brisbane with Beaufort carrying maintenance personnel, for comparisons with Hap
28-Jul-43 AR269 Anti G suits, to Brisbane with Beaufort carrying maintenance personnel, for comparisons with Hap
4-Aug-43 AR621 No engine roughness with English cowling, tests with EE610 continuing. Being fitted with radio in preparation for the arrival of the Hap.
4-Aug-43 EE610 English cowl fitted, 1/32 inch difference in cowl/flap distance between EE610 and AR621, flight tests to commence. Airscrew packing tests continued with satisfaction. Wooden belly tank tests completed, report submitted.
11-Aug-43 EE610 Airscrew packing tests continued with satisfaction.
18-Aug-43 EE610 Airscrew packing tests continued satisfactorily.
18-Aug-43 AR621 Comparative tactical trials with Hap continuing at Archerfield.
1-Sep-43 EE610 Tests continuing to find cure for high altitude engine roughness with English cowl fitted. Airscrew packing tests continued.
1-Sep-43 AR621 Test carried out using new electrically controlled valve for G-Suit.
8-Sep-43 EE610 Tests continuing to find cure for high altitude engine roughness, an English made temperate cowl has been found and is being fitted. Airscrew packing tests continued, leaking after only 19 hours flying.
8-Sep-43 AR621 Test carried out using new electrically controlled valve for G-Suit. Valve not releasing correctly, equipment removed and being modified.
27-Oct-43 EE610 Belly tank installation attachment now satisfactory by stiffening the tank adjacent to the attachment pin, can withstand over 5 G
10-Nov-43 EE610 Belly tank installation tested to 7 G
24-Nov-43 JF394 mark VIII level speed, climb and take off tests, engine surging at high altitude.
8-Dec-43 A58-315 Airscrew surging, possibly due to oil frothing at high temperature
8-Dec-43 A58-110 P.8 Compass, needle sticking against glass cover if much bank applied.
15-Dec-43 A58-315 Climbing tests delayed due to unserviceablity of Cine Camera in automatic observer. Durability test on locally made tyres begun.
22-Dec-43 A58-315 Durability test on locally made tyres, worn through to canvas in 10 flights using concrete taxyways and runways.
29-Dec-43 A58-315 Flown to Gorrie for tropical test of modified oil cooler, which did not give enough cooling in warm air. Locally made tyres do better on non concrete runways.
5-Jan-44 A58-315 Oil cooling tests, pressure and temperature gauges fitted throughout the system plus another form of restriction on the air outlet.
12-Jan-44 A58-10 Drogue towing, use of English pully has eliminated cable breakages, tests now on drogues, to eliminate their unsteady streaming.
2-Feb-44 A58-303 Modification found successful on A58-315 has been done on several other aircraft which have been flight tested. The effect on oil temperature varies between aircraft, 65 to 80 degrees, now trying for a ground test of all such viscosity valves.
2-Feb-44 A58-315 Modification found successful on A58-315 has been done on several other aircraft which have been flight tested. The effect on oil temperature varies between aircraft, 65 to 80 degrees, now trying for a ground test of all such viscosity valves.
2-Feb-44 A58-10 Drogue towing, stronger drogues break cables, more flexible cable has been procured.
2-Feb-44 A58-10 G-suit equipment installation held up by intermittent arrival of parts
2-Feb-44 A58-303 G-suit equipment installation held up by intermittent arrival of parts
8-Mar-44 A58-303 Tests to be done of 1 piece G-suit made by Dunlops. Photographic recorder of G pressure, maximum G and airspeed being installed.
15-Mar-44 A59-315 Fuel consumption tests begun
29-Mar-44 A59-315 Performance tests done. Minor misfiring at cruise power noted and will be investigated.
29-Mar-44 A58-303 G-Suit. Device to restrict elevator movement at a certain pre-determined G value is being installed.
8-Jun-44 A58-303 High G tests with G-suit begun
29-Jun-44 A58-303 High G tests with G-suit, further tests with new equipment
19-Jul-44 A58-110 Reconditioned Merlin 46, 8 hours flown, satisfactory, no glycol leaks.
26-Jul-44 A58-303 High G tests with G-suit, tests completed
26-Jul-44 A58-110 Reconditioned Merlin 46, glycol leak at 60 degrees C has suddenly increased, leaking all the time. No further operation of the engine.
16-Aug-44 A58-110 Second Reconditioned Merlin 46 fitted, glycol leak after 2 hours 25 minutes flying. Report on first engine being forwarded.
13-Sep-44 A58-315 RG 5/3 spark plugs, still satisfactory
15-Nov-44 A58-303 Photographic recording unit for G-Suit tests completed and fitted at 1 APU.
22-Nov-44 A58-303 To test American G.3 G-Suit.
13-Dec-44 A58-303 Test American G.3 G-Suit. 12 preliminary flights, suit estimated to give 2G protection.
20-Dec-44 A58-599 Carriage of 300 pound wing bombs, carriers and belly tank fitted.
20-Dec-44 A58-303 American G.3 G-Suit. Initial tests completed.
3-Jan-45 A58-303 Test American G.3 G-Suit. Testing the G2 valve versus the USN Cornelius valve.
10-Jan-45 A58-499 Carriage of 300 pound wing bombs, awaiting trials with bombs fitted.
14-Feb-45 A58-499 Carriage of 300 pound wing bombs, deflectors for spent cartridge cases being prepared
7-Mar-45 A58-499 CO contamination, equipment tests, slight modification needed. Deflectors for spent cartridges fitted, 300 pound wing bomb racks.
14-Mar-45 A58-601 HF VIII performance test, level speeds at combat power done.
14-Mar-45 A58-499 CO contamination, equipment tested, slight modification needed. Low power speeds completed, deflector to prevent bomb fusing by spent cannon cases being tested.
21-Mar-45 A58-499 Deflectors for spent cartridges flight tested with 300 pound wing bomb racks. Mock up of coolant system done, tests on corrosion problems begun.
28-Mar-45 A58-601 HF VIII performance test, preliminary fuel consumption runs
28-Mar-45 A58-499 Deflector to prevent bomb fusing by spent cannon cases being tested, various modifications done. Mock up of coolant system completed, tests about to start.
5-Apr-45 A58-601 HF VIII performance test, fuel consumption runs done.
12-Apr-45 A58-601 HF VIII performance test, fuel consumption runs at 20 and 30,000 feet done
12-Apr-45 A58-499 Deflector to prevent bomb fusing by spent cannon cases satisfactory, position error with 250 pound bombs calculated.
18-Apr-45 A58-601 HF VIII performance test, take off tests done. Mock up of coolant system completed, 40 hours of running with uninhibited glycol and water mixture.
25-Apr-45 A58-499 300 pound wing bombs, no further work for last 2 weeks, aircraft unserviceable
25-Apr-45 na Mock up of coolant system completed, 60 hours of running with uninhibited glycol and water mixture. No results yet
16-May-45 A58-499 300 pound wing bombs, aircraft serviceable, flight trials underway.
16-May-45 na Coolant system corrosion, CAC aerater header tank tested, working satisfactorily.
23-May-45 A58-499 300 pound wing bombs, Rated and combat power level speed runs done with 250 pound bombs and 30 gallon belly tank, level speeds at optimum range, -2 pounds/square inch boost at 1,800 rpm, this finishes flying work.
23-May-45 na Mock up of coolant system completed, 60 hours of running with uninhibited glycol and water mixture. No results yet
Apr-46 A58-717 Tropical trials with improved flexible fuel tank, test tank fitted, aircraft to be sent to Darwin
Early Australian Spitfire imports and RAAF strengths, to end 1943
14-Aug-1942 6
19-Oct-1942 6
21-Oct-1942 5
27-Oct-1942 6
28-Oct-1942 10
29-Oct-1942 7
30-Oct-1942 9
2-Nov-1942 4
4-Nov-1942 16
5-Nov-1942 1
10-Nov-1942 6
Strength excludes aircraft awaiting official write off but includes still to be assembled. Date is week ending. Delivered, lost and assembled are cumulative figures.
Date / Deliv / Lost / Strength / Assembled
5-Sep-42 / 6 / na / na / 6
9-Sep-42 / na / na / na / 6
16-Sep-42 / na / na / na / 6
23-Sep-42 / na / na / na / 6
30-Sep-42 / na / na / na / 6
9-Oct-42 / na / na / na / 6
16-Oct-42 / na / na / na / 6
23-Oct-42 / na / na / na / 6
30-Oct-42 / na / na / na / 6
6-Nov-42 / na / na / na / 14
13-Nov-42 / na / na / na / 29
20-Nov-42 / na / na / na / 45
27-Nov-42 / na / na / na / 62
4-Dec-42 / na / na / na / 73
11-Dec-42 / 103 / 3 / 100 / 76
18-Dec-42 / 103 / 3 / 100 / 82
25-Dec-42 / 103 / 4 / 99 / 94
31-Dec-42 / 108 / 4 / 104 / 95
8-Jan-43 / 108 / 4 / 104 / 97
15-Jan-43 / na / na / 104 / 101
22-Jan-43 / 108 / 5 / 103 /
29-Jan-43 / 114 / na / 108 / 106
5-Feb-43 / 114 / 4 / 107 / 106
12-Feb-43 / 114 / 4 / 107 / 107
19-Feb-43 / 114 / 9 / 105 / 107
26-Feb-43 / 118 / 11 / 107 / 107
5-Mar-43 / 124 / 11 / 113 / 110
12-Mar-43 / 132 / 10 / 119 / 112
19-Mar-43 / 145 / 10 / 127 / 114
26-Mar-43 / 144 / 10 / 125 / 115
2-Apr-43 / 144 / 11 / 125 / 115
9-Apr-43 / 144 / 15 / 125 / 115
16-Apr-43 / 151 / 18 / 132 / 115
23-Apr-43 / 165 / 18 / 145 / 119
30-Apr-43 / 165 / 17 / 146 / 12
7-May-43 / 165 / 18 / 132 / 140
14-May-43 / 165 / 18 / 132 / 147
21-May-43 / 171 / 18 / 138 / 157
28-May-43 / 171 / 18 / 137 / 157
4-Jun-43 / 171 / 19 / 135 / 159
11-Jun-43 / 171 / 28 / 135 / 163
18-Jun-43 / 176 / 31 / 138 / 166
25-Jun-43 / 177 / 34 / 135 / 167
2-Jul-43 / 195 / 37 / 151 / 168
9-Jul-43 / 202 / 37 / 141 / 172
16-Jul-43 / 202 / 39 / 139 / 174
23-Jul-43 / 202 / 44 / 138 / 186
30-Jul-43 / 202 / 44 / 142 / 192
6-Aug-43 / 218 / 45 / 158 / 198
13-Aug-43 / 228 / 46 / 167 / 199
20-Aug-43 / 228 / 46 / 165 / 205
27-Aug-43 / 228 / 46 / 165 / 217
3-Sep-43 / 228 / 51 / 165 / 218
10-Sep-43 / 228 / 53 / 162 / 222
17-Sep-43 / 228 / 53 / 161 / 222
25-Sep-43 / 228 / 54 / 160 / 222
1-Oct-43 / 229 / 57 / 158 / 223
8-Oct-43 / 235 / 63 / 162 / 225
15-Oct-43 / 235 / 66 / 163 / 225
22-Oct-43 / 260 / 69 / 186 / 225
29-Oct-43 / 260 / 72 / 186 / 226
5-Nov-43 / 260 / 72 / 186 / 226
12-Nov-43 / 265 / 73 / 190 / 230
19-Nov-43 / 265 / 73 / 188 / 239
26-Nov-43 / 265 / 76 / 186 / 248
3-Dec-43 / 271 / 77 / 191 / 252
10-Dec-43 / 271 / 77 / 190 / 252
17-Dec-43 / 273 / 77 / 192 / 253
24-Dec-43 / 273 / 77 / 191 / 255
31-Dec-43 / 278 / 78 / 194 / 255