Geoffrey Sinclair
Staff Sergeant
- 922
- Sep 30, 2021
Which reference do the figures come from? For a start they imply no Hurricanes built between 10 June and 29 September 1939.Hawker ordered material before the contract was placed.in 1936.
The last of the 600 plane order (430 with fabric wings) was competed June 10th 1939.
The second contract was placed in 1938 for 300 planes. Started Sept 29th 1939 and finished on May 1st 1940.
3rd contract placed also in 1938. for 500 +44 attrition. Started Feb 21s 1940 and finished July 20th 1940.
Gloster 500 plane contract was also from 1938. Deliveries start Nov 1939 and finished April of 1940.
Some rather different results from the production reports and RAF contract cards. Cumulative official production by Hawker to end June 1939 was 464, end September it was 594. To end February 1940 it was 884, to end March a total of 951. First official production from Gloster was in October 1939, cumulative official production to end April 1940 was 225, end June it was 448, end July it was 568.
Contract 527112/36, Requisition 26/36, Maker Hawker, Quantity 600, Note: Includes 60+20 for other governments. Completed 8 Nov 1939. L1547 to L2146
Contract 751458/38, Requisition 56/38, Maker Hawker, Quantity 300, Note: Includes 12 for other governments. Completed 15 Feb 1940, N2318 to N2729 (167 Brooklands, 133 Langley) The first Langley built Hurricane was N2318, first taken on charge date was N2320 on 4 October 1939.
Contract 962371/38, Requisition 195/38, Maker Gloster, Quantity 500, Note: Completed 13 Jul 1940, P2535 to P3264
Contract 962371/38, Requisition 195/38, Maker Hawker, Quantity 292, Note: Brooklands, completed 20 Jul 1940, P3265 to P3984 (500 a/c), P8809 to P8818 (10 a/c), R2680 to R2689 (10 a/c), W6667 to W6670 (4 a/c)
Contract 962371/38, Requisition 195/38, Maker Hawker, Quantity 232, Note: Langley, completed 17 Jul 1940 (serials in Brooklands line)
For reference, P8809 to P8818 (10 a/c, Brooklands), R2680 to R2689 (10 a/c, 2 Brooklands, 8 Langley), W6667 to W6670 (4 a/c, Langley). So the third Hurricane contract was split between Gloster and Hawker, I assume Gloster being the subcontractor.
Contract B19773/39, Requisition 195/38, Maker Gloster, Quantity 100, Note: Completed 9 Aug 1940, R4074 to R4232
The 60+20 comment in contract 527112/36 is because the Canadian order received its own contract. Contract 966177/38, Requisition 215/38, Maker Hawker, Quantity 20, Note: For Canada, originally part of contract 527112/36
It is probable Langley only produced metal wing Hurricanes, Gloster was metal wing. N2426 is was the last of the second order with fabric wings. L1877 was the first with metal wings, next was L2026, various other L serial aircraft are marked metal wings.