Today I built the mizzen mast and substituted a bigger radar system at the top. The one that was supoosed to go there was tiny and didn't go well. I have this sheet of miscellaneous WW2 radars from Tom's Model Works and took advantage of it.

I also built the secondary yardarm that goes under this mast. The mast is 3/64" brass rod, the platform was turned on the lathe and the ladder is from my left over Eduard set. The Eduard ladders as narrower and seem more prototypical.

I'm getting really good at making the hybrid yard arms. This was was a piece of cake even though it was a much smaller build than the main yard.

Essex_Mizzen_Mast.jpg


I added a soldered bushing on the mast's base to increase the gluing area and enlarged the hole in the funnel to accept. I enlarged it a little too much and glued in some plastic filler strips. I'm going to J-B Weld this in place when it's time to put it together. It also will have guitar string guy wires and will need an outrigger at the funnel's rear to accept the back guy. Similarly to what I did on the Missouri.

Flag_halyards_1.jpg


I started putting on the island's railings and of course, the inclined stairs got a bit beat up. The GMM stairs are particularly delicated and I kept bumping into the their railings. I'm running out of the Eduard version (a little more rugged) and am going to buy more of them. I also lost a few porthole eyebrows and one WTD. I'll go back and fix these later.

Essex_Railing_Install_1.jpg


Tomorrow, I'll keep adding details...
 
Yes! Toady was really the definition of fiddly bits.

I have only one picture today. That's because things went soooooo badly that one picture was all that was worth publishing.

It all started with trying to bend the stair treads on the GMM PE inclined ladders using an idea that was published on the Ship Modelers Forum. I found it searching to buy more inclined ladders since I was destroying them faster than creating them. I found that GMM sells a fret with just ladders. The idea to bend the steps didn't work on GMM or Eduard ladders, but was designed for Tom's which actually makes a provision in the etching to enable step bending. I did have some Tom's steps, but the fret was badly etched and the details were too thin a cross-section to permit adequate handling.

In my searching for more inclined ladders to scavenge, I found a neat piece of Eduard PE that could be pressed into action as the outriggers for the mizzen mast. I drilled it to accept the mizzen base and then drilled it with a microscopic 0.015" carbide drill to accept .011" guitar string. Believe it or not, I did not break this drill and did drill both holes. Now that I figured out how to take really tight closeups, that guitar string looks huge. It ain't! The extra solder was deliberate to reinforce the Eduard etched bend lines since I wasn't bending those angle pieces as they should have been if used as the piece was intened to be use.

Essex_Mizzen_Outrigger.jpg


When I attempted to solder the mast into this hole, it didn't take. Furthermore, the yard arm detached. That when the proverbial stuff hit the fan.

As I messed with the yard arm, the PE laminate started separating and it was getting munged up pretty badly. I decided to remove the bad PE and use the other yard arm PE that I had. When GMM sent me the new main yard PE it was attached to part of the fret that also had the smaller PE yard arm. I soldered this onto the existing made yard and then went to solder it to the yard arm. Oh... and the ladder broke off.

Each time I attempted to solder the yard on the mast had a problem. They were (and could be more than one problem at a time):

  • Off center
  • Canted
  • PE not oriented correctly vertical
  • PE separating from the yard arm
I tried to put this together four times (at least), and of course, the PE was getting munged up like the first one.

Then I tried to free hold the assembly in the RSU's tweezers to just heat it enough to move the yard to the correct orientation, and the whole deal flew out of the tweezers. I found both parts. Then in another attempt to hold the mast in the tweezers since the platform at the top had re-melted and was now canted, and the mast flew out of the tweezers again, and the sound I heard from across the shop was the sound of a piece of brass entering the quantum rift. I wasn't able to find it. I'll find it where the radio tower ended up.

So now I'm starting all over again. This time I won't have PE to add to the yard, but I'll figure something else out. All in all, an almost totally frustrating day. You have them sometimes.
 
The nice thing about scratch-building is that when you really screw something up you have the abilty and where-withal to make it again, and that's what I did with the mizzen mast. This time I formed the yard out of a solid piece of 1/32" brass square stock. I clamped the piece in a vise grip and ground the tapered portions with the 1 inch belt sander and then finished up by hand. The mast was made the same as the first on with one exception, I turned the base to be a tighter fit in the hole drilled in the funnel.

Essex_Mizzen_Mast_2_Parts.jpg


To solder the yard in place I clamped the mast to the solder pad and went at it with the RSU. Again it took 3 tries (at least) to get it centered and square to the mast. But this time, the solid bar without the PE was a bit easier to manipulate. That being said, I also soldered a piece of bent 0.011" guitar string underneath to act as a place to belay the flag halyards that go up to this mast. That piece of wire was a pain. It de-soldered a few times, got lost 2 times (made new ones) and finally got it to behave.

Essex_Mizzen_Mast_2_Yard_Solder.jpg


The first time I soldered it with TIX, but TIX seems to have a problem. If you get the joint soldered right the first time, it holds nicely. But if it breaks away and you try to resolder, it seems not to hold at all. I tried several times to get it to work, and then reverted the Kester soldering paste which is a higher temp solder. I was reluctant to use a higher temp since I didn't was to de-soldered the platform, or (and this would be worse) de-solder the radar screen. To help forestall this, I clamped a spring tweezers between the heat and the screen to act as a heat sink. It worked. It never de-soldered through these multiple attempts.

I added back the ladder and the base using CA to not tempt the fates and keep the soldered stuff soldered.

Essex_Mizzen_Mast_2_Fin_1.jpg


It looks kind of crude in this extreme closeup. Since it about 1/4 this size, and painted it will look okay. The Missouri's masts looked the same before they were painted.

Essex_Mizzen_Mast_2_Fin_2.jpg


Next up I'll be finishing up the railings and steps on the island and then start putting it all together prior to painting. Glad to have this mast finished. I wasn't happy on Friday.
 
Thank you fellas!

A pretty good day...

All work was entirely on the island. I added some Eduard small ladders to a step on the upper decks. Eduard PE instructions are among the best (if not the best) so I printed out their Essex set's instructions to use on this model. Their set is for the Ticonderoga, but much is very similar. I had these small ladders left over from the MO, but they were still too long so I cut them shorter.

Essex_Small_Ladders.jpg


I made some long platform railings using GMM's railing stock and some PE Fret brass from Tom's MW. I soldered the two together and then CA'd them to the island.

Essex_Soldered_Railing.jpg


It should have been one long 8-section railing. I made a 4-section railing set and then checked my photos and realized that the catwalk went all the way to the WTD on the island side. I then made another 4-section piece. As it is, I would have had trouble soldering that long of a railing to that long of a walkway. There is a loudspeaker that goes right in the middle of that rail which will hide the joint between the two.

I changed the contour of the left most ladder way since it didn't allow a GMM inclined ladder to correctly sit. I took off part of the plastic rail and then widened the space and put a newly bent ladder in. This worked much better and cleaned up a mess.

IMG_2161.jpg


I decided it was time to add the mizzen mast and its guy wires since it would take some manipulation and I didn't want any more stuff in the way.

I glued in the mast with thin CA and then back filled with medium CA. After it kicked, I built the outrigger out of 0.021" and soldered it using the RSU plus standard 60/40 rosin core solder, held in place on the soldering pad. It was an easy build and believe me, I needed an easy one. I cut the legs to length and drilled the funnel with a #75 carbide drill for the three legs. I angled all three holes to correspond to the legs' angles.

Essex_Guy_Outrigger.jpg


I glued the outrigger in with thin CA.

To hold the guy wires (high E guitar string - 0.011" dia.) I used a divider to space out their locations and drilled with a 0.0105" carbide drill. This drill is so small that if you pick it up the wrong way, accidentally touch the side of the drill, or drop the pin vise on your leg, the drill will break and disappear. It will also put a needle injury on your thigh. Ask me how I know...

I put a kink in the bottom end of the wire, fit it in the hole and then cut the length so it tucked under the platform on the antenna mast.

Essex_Guy_Wire_Fit.jpg


I used this length to approximate the length of the other foreward guy, and then used J-B Weld to glue them in place. I put a kink in the bottom of the rear guy so it would sit flat on the outrigger, measured its length and glued that in place also.

Essex_Guy_Install.jpg


This all has to cure overnight. Tomorrow, I continue detailing the island and get ready to start adding the big assemblies before painting.
 
The Island is coming together... in fits and starts, but it is getting together. I first added a very small rail at the stair landing at the top of the left most ladder. I find that small rails like this, instead of being easy are a royal pain in the butt. They're very springy and if you grab them the wrong way they fly. They also want to glue too quickly before they're sitting just so... and then when you just want to tweak them a little teeny bit, they fall off and you have to start over again. I did that five times before I got one to be where I wanted it without being a distorted mess.

Boy, these models are not meant to look at this closely...

Essex_Little_Railing.jpg


The J-B Weld cured nicely for the mizzen mast guy wires so I was ready to start adding more stuff. Next up was the whistle platform. In this case, I soldered a piece of flattened 0.021" brass wire for the mounting pin. I also did the same on another small antenna platform. I am so glad that I spent the effort to add these brass pins to the PE platforms. The angle brackets are useless, and are almost always bending and breaking off. You CAN NOT DEPEND ON THEM TO ACTUALLY SUPPORT THE PLATFORM! The whistle was scavenged from the old MO and I drilled the back of it to accept a piece of fine gauge solder that simulates the steam line to the whistle. I the line originates in the funnels fore port side. I can probably dress that line a bit better.

Essex_Whistle_Deck_Install.jpg


And then it was time to add all the rest of the antenna systems. The SK's railing was a mess and was interfering with installing it properly. I trimmed away part of the funnel top plate and then re-arranged the ends of the railings to wrap onto the funnel. It's not great, but cutting the GMM rails in the middle creates a non-controllable mess with the three bars just flopping around. It doesn't work. And I've tried soldering another vertical post in the middle to give a shorter section. It didn't work, but it could. I just have to perfect it a bit. CA'ing the vertical is a non-starter. The 0.032" pins worked, but they were a bit of push into the holes which worried me that I might use too much force, slip and screw up several hours of work on those antennas.

The tri-mast went in without a hitch. And I added the piano wire guys to that top mast on that platform too. I didn't attempt to drill any tiny holes in the brass. All that would have done was break a $1.50 carbide tiny drill and probably destroyed some antenna or another, so I just placed them there and will led the J-B do its stuff. It's starting to look really cool especially if you don't dwell on all those twisted railings. When it's painted and rigged with radio wires and flag halyards it's going to be very convincing.

Essex_Topmast_Guys.jpg


While the J-B was setting up, I started detailing the structure that sits directly aft of the island: a two-deck tower that supports a 40mm quad gun tub and director. My research shows a couple of vertical ladders, a WTD at the 2nd level, and a landing and inclined ladder at that door. I was having a time making the small platform, again because you can't really have GMM rails in half-sections. I get this finished tomorrow and show it.

I like building aircraft carriers only for the islands and all the stuff hanging on them. As aggravating it is to build all this brass stuff, the end result is very pleasing and keeps me going. I swore after the Missouri that I wouldn't put myself through another balls to the wall PE ship build and yet, here I am doing it again. When it's going bad it drives you nuts, but then when you finish something it's worth it. Unlike detailing a hangar deck where no one will ever see anything, building all this island gingerbread really pays off.
 
Thanks! And yes, they're worth it. As my wife says, "Stop complaining, it's your hobby...not work! Nobody's telling you that you have to do it." She's a smart lady.

After sleeping on the problem of making that little ladder platform, I did attempt #4. This time, I did two things differently: I found a piece of railing in the leftover Mo set that was a short railing with another even shorter segment. And then I shaped a brass platform to match this configuration. I also added to folded angles to act as brackets to increase the gluing area many fold and solve that problem of not relying on the railing itself to aid in gluing. This closeup makes it look terrible. It's really not bad...a little off kilter, but it will work. The inclined ladder has to go on after it's glue to the deck... I think. I may want to glue it on now so I can paint it before installing it.

Essex_Gun_Tower_Platform.jpg


I then added the 40mm gun mount and the MK 51 director so this piece is ready for paint (except for the aforementioned inclined ladder).

Essex_Gun_Tower_Complete.jpg


The latest guy wire gluing went well too with the guitar strings firmly attached to the mast and deck. I then decided to add the wind deflectors. The GMM wind diflectors looked to me as a complete exercise in futility. It consists of some etched strips with little relief cuts and then a ton of little pieces to serve as the supports. I cannot, for the life of me, figure how to a) attach all those parts without going nuts, and b) then bending it around the deck rails and glue it in place without all of those tiny pieces breaking loose. I thought about soldering them in, but I'm not that good.

Essex_GMM_Wind_Diflectors.jpg


This image is bigger than it actually is. I can even imagine cutting all those pieces off the fret without losing half of them to the Rift. Sometimes with PE, just because you can draw it, expose it and then etch it, doesn't mean a mortal (like me) can build it.

So I did a plan B. You can really see the slats holding it on, so I took some wine bottle foil and a piece of 0.020" Evergreen round styrene rod to use as a spacer. I measured the PE strip at 0.037" and used the same digital caliper to scribe a line of that distance on the foil. I held a straight edge up to that line and CA'd the styrene to the foil, BEFORE CUTTING THE FOIL STRIP since I could not imagine getting the two aligned with that wiggly, strip moving all around. When the CA set I then cut the foil with a sharp #11 blade and the same straight edge.

Essex_Wind_Deflector_Construct.jpg


By using the styrene as the spacer I was able to use Tamiya cement to glue it to the ship.

A little forming and shaping was needed once it was glued. Again, once it's painted it should do what was intended.

Essex_Island_Wind_Deflectors.jpg


Lastly, I started laying in all the added stuff on this complicated sub-assembly: Mk 51 directors, signal and search lights, MK 38 directors, 40mm guns, etc. Starboard Side -

Essex_Island_Strbrd_Side_Status_2.jpg


Port side -

Essex_Island_Port_Side_Status.jpg


I did straighten out the steam line to the whistle. There's also a smaller diameter pipe going to that same area that I may add. Still to do are all the 20mm gun sets for the island (and the rest of the ship). One of the side-of-funnel searchlights is missing. There were supposed to be two of them, but the sprue attachment was very weak on these parts and both fell off (one of each of two identical sprues). I captured one for safe keeping, but have lost one. I'm going to scratch build one. If it works well, I may scratch build both. It goes in that sponson with the half railing next to the funnel.

I almost had a heart attack... notice how close my outrigger for the mizzen mast aft guy wire is to the Mk 38 director aft of the funnel. It just fit. In real life this outrigger would have been much, much smaller. I could have made it smaller since I was just winging it. I didn't even think about the director going so close.

I'm going to paint and detail all of this before gluing it to the deck. I may also add all the rigging that is contained within the island since it's much easier to do this while holding it my PanaVIse than to do it leaning over the ship.
 
Spent a lot of time today making some very small things...

I made another searchlight to replace the one that's missing. I turned a cylinder the diameter of the prototype, 36" = 0.100" approx. at 1:350. I then turned a pedestal. This came out nicely, but as you'll see it's a bit tall. I could have made it shorter, but didn't feel like making another. The only way you know is if you look at the ship head-on and see port and starboard lights at the same time.

Before parting the cylinder off the stock, I took it out of the lathe, put it in a v-block, filed a flat on the circumference so the center punch and drill would skitter off the circle, and then drilled with a 0.032" carbide drill in a pin vise. I had to drill through the center hole and had to be careful to keep it aligned and not break it. I use Tap Magic for brass when drilling and turnind which helps prevent grabbing which is notorious when machining brass with positively-raked cutting tools. Normally, brass tools are ground with 0 or negative rake angles to scrap the surface rather than cut into it. The rake angle is the back slope of the cutting edge. Positive rake has an acute angle falling back from the cutting lip. Even with drills, if they're large enough to do this, you can grind a small flat behind the cutting edge to reduce the rake angle.

I made the bail with a piece of PE fret brass and turned the base with a 0.032" base pin and pin for the bail. I needed to set the hole spacing for the trunions. The cylinder was .100", and the trunion pins would lie on the diameter, so I multiplied .100 X pi, and then cut that in half and added 0.020" for some clearance. I could have added more, but the bail did fit over the pins. After soldering it all together, I trimmed the bail and filed off the trunions. I filled the center hole with solder to make a face. I was going to leave the hole, but the trunion passed through the middle.

Essex_Search_Light_Build.jpg


Here's the installed search light.

Essex_Search_Light_Install.jpg


Next I built the GMM PE loudspeakers. They're a three-part affair with a folded box, a perforated screen and a small folded bracket. I decided to solder these together after messing around, unsucessfully, with CA. The first one I made (which eventually flew out of a tweezers into the Rift) I soldered the screen and then attempted to solder the bracket. This was a mess. The next one, I soldered the bracket first and then soldered on the screen. This worked. But I lost a couple of the brackets, so the next two I made a bracket with a strap of PE brass. This actually worked even better. You can't see that microscopic bracket anyway.

So I only had three of them at that moment. I CA'd the first one to the front wall of the flag bridge as shown in one of my diagrams. The other goes on the rail in the island's middle. This didn't want to settle down with CA, so I went with J-B. Since it sets very slowly, I laid the island over almost horizontal by swiveling the Panavise base into that position. It will be cured on Monday when work begins again. You can just see it below the radar antenna racks facing upward. The 3rd loudspeaker, which was supposed to go on the aft end of the island, flew out of my tweezers on the way to put some CA on its bracket and went into the Rift.

Essex_Loudspeakers.jpg


I started building the 20mm gun sets. GMM includes four PE pieces for each gun: shield, shoulder rests, gun sight and elevating wheel. Of these, the easiest to install was the shield, but I did have to rough up the brass at the glue site to give the CA something to stick to. I also put on a set of shoulder rests. I tried, successfully at first, to install the tiny gun sight, but it fell off and then got lost. I also tried to install the hand wheel, and it too fell off. So it took quite a while to get one done. I got the second one underway before dinner time. I've got to build 13 of them just for the island. I have a full set of 20mm PE guns left over on my MO Eduard set. These are a folded deal that already includes the shoulder rests, but lacks a base. The base pin is about 0.020" and could work (maybe) with the Trumpeter bases, or I could just turn a set of custom bases and solder the whole deal together including the shields. I have to think about this over the weekend.

Essex_20mm_parts.jpg


That's an #11 blade in the picture for scale comparison, so you can get a good idea about just how small that gun site is AND you have to rotate the circle site so it's perpendicular to the barrel. It just has that tiny base to hold it to the gun barrel. It's not a pretty thing and I'm not so sure it will be successful, at least for me. I am sure there are builders some where out there in this wide world that have the steadiness and techniques to build these micro-PE assemblies.

Here's the completed one. The Trumpeter barrel is WAY out of scale. The Eduard ones are much closer to scale, but they lack that base. Nothing's perfect. I've looked at some of those Korean and Chinese PE company products which have turned barrels and so much detail, but I can't figure out how you'd build the darn things. At 1:200, you'd have a chance, but at 1:350, it seems almost impossible, based on my experience.

Essex_1st_20mm.jpg
 
Thanks! That's in the eye of the beholder... Those severe closeups unnerve me a bit. It's like looking at a cockroach's face in macro-photographs. The iPhone camera is actually remarkable, that it can focus from infinity to macro with the same tiny lens.
 