It is a debacle but the Me 210 was far from dead.
Despite considering ditching the Me 210 for the Ar 440 a 1st April 1942 re-start date is considered for the Me 210 program in the same memorandum that had halted production!
Messerschmitt are ordered to modify six aircraft with a lengthened fuselage, slats, internally balanced elevators, autopilot to a zerstorer configuration but without armour for a rapid testing program.
Another ten are to be similarly modified complete with armour for an extended series of tests at Rechlin.
The deadline for this is 16th March 1942. Willy Messerschmitt agreed to this despite being aware that it was unrealistic and impossible.
25th March 1942, Messerschmitt, a man battling to keep the project alive, writes to Test Center Director Franke.
"You are certainly aware that the field is having problems with the Me 210 and that, contrary to all expectations, these are mainly attributable to stalling."
Talk about economical with the truth! He continued.
"The defects already known (ground looping on landing, unpleasant handling of the elevators) have been taken into consideration by lengthening the fuselage and fitting a counterbalanced elevator, both of which were approved by the test centre and, after just a few flights, were considered satisfactory by both the field and the test centre. The remaining criticisms of the landing gear (hydraulics, weapons etc) are fundamentally engineering issues and can be remedied in the near future."
14th April 1942 Oberst Vorvald reports to Milch that the 6 Me 210 test examples are not finished and will not be finished by Messeschmitt until 20th April. The delay is caused by an increase in the number of changes required from 4 to 40.
Makes me wonder what exactly Willy was basing the assertions in his earlier letter on, at least one aircraft was presumably modified, at least partially.
19th April 1942. Milch states that "the Me 210 will no longer be a significant player in 1942." He doubts whether it will ever go into production. Everything depends on the test programmes and series production can't start until four months after completion of the programme.
21st April 1942. Milch reports that the Me 210 is to be dropped from production programmes on the express orders of the Reichsmarshall. The 16 test examples are to be completed and tested. All further work to cease immediately.
The Gotha and Luther companies are to be withdrawn from the Me 210 license building programme for good.
The air attache at the Hungarian Consulate is to be officially informed that Me 210 production is frozen "for technical reasons".
Messerschmitt is officially informed of this decision, by the RLM, on 25th April 1942.
At this time 94 Me 210s had been completed at Augsburg and another 258 at Regensburg. At both plants a total of 540 Me 210s were at various stages of construction. Materials for large scale series production had already been delivered to the plants. Close to 4,000 employees were left standing around with nothing to do.
It is almost inconceivable that such a state of affairs was allowed to develop at such a crucial stage of the war. 1942 is often seen as a turning point, not least due to the faltering campaign in the east and then the debacle at Stalingrad later in the year. A situation like this in the aircraft industry, as the Anglo-Americans geared up for their massive aerial assault on the Reich can hardly have helped.
Another swipe of the axe, and thus ended the second episode of the saga.
The Me 210 was still not dead though.
Cheers
Steve